Free tool · Landlord · England

Section 13 Rent Increase Calculator (Form 4A)

Find the earliest date a rent increase can start, or check a date you have in mind, under the Renters’ Rights Act 2025 rules.

Updated November 2026 · England only · Free, no sign-up
Each rental period starts on this day of the week or month.
Add time for post: the notice counts from when the tenant receives it.
Leave blank to see the earliest date the new rent can start.

For private assured tenancies in England with rent paid monthly or more often. A guide to the rules only, not legal advice. Always check the notes on the current Form 4A on GOV.UK.

The three rules the calculator checks

Since 1 May 2026, the only way to raise the rent on a private assured periodic tenancy in England is the Section 13 process, using Form 4A on GOV.UK. The notes on Form 4A set out when the new rent can start:

  1. Two months’ notice. The notice must be served at least two months before the new rent starts.
  2. Once a year. The first increase cannot start until 52 weeks after the tenancy began. Each later increase must start at least 52 weeks after the previous one. You can serve the notice before the 52 weeks are up.
  3. Start of a rental period. The new rent must start on the first day of a rental period, so on the day rent is normally due.

The calculator takes the later of the 52-week date and the two-month date, then moves forward to the next rent day.

If the tenant disagrees

The tenant can refer the proposed rent to the First-tier Tribunal if they think it is above the market rent. The tribunal must receive the application before the start date in the notice. The tenant does not have to pay the new rent until the tribunal decides, and will not have to pay more than the rent you proposed. The tenant and landlord can also agree in writing to change or delay the increase. See the GOV.UK guide to rent increases.

Next step
Section 13 Rent Increase Notice (Form 4A) pack
Fill-in Form 4A guidance, cover letter and serving record.
See the pack →

Frequently asked questions

How much notice does a landlord need to give for a rent increase in England?

At least two months. The Form 4A notice must be served at least two months before the date the new rent starts.

How often can rent be increased under Section 13?

Once a year. The first increase cannot start until 52 weeks after the tenancy began, and each later increase must start at least 52 weeks after the previous one. The notice itself can be served before the 52 weeks are up, as long as the new rent does not start until they have passed.

Does the new rent have to start on a particular day?

Yes. The new rent must start at the beginning of a rental period. For example, if a weekly tenancy started on a Monday, the new rent must start on a Monday; if rent is due on the 5th of each month, the new rent starts on the 5th.

Can my tenant challenge a Form 4A rent increase?

Yes. The tenant can refer the proposed rent to the First-tier Tribunal if they think it is above the market rent. The tribunal must receive the application before the start date in the notice. The tenant does not have to pay the new rent until the tribunal decides, and will not have to pay more than the rent the landlord proposed.

Does this calculator work for Wales or Scotland?

No. Form 4A and the Section 13 rules covered here apply to private assured tenancies in England. Wales uses occupation contracts under the Renting Homes (Wales) Act 2016, and Scotland uses private residential tenancies, each with their own rent increase rules.

Add this calculator to your website

Landlord blogs, letting agents and advice sites are welcome to embed this free calculator. Copy the code below into your page.

Related tools and guides

Last checked against the Form 4A notes on GOV.UK on 26 November 2026. This tool explains the timing rules only. It is not legal advice.

⚡